Matthew Collins
Member
I’m mid-build on a rectangular concrete block pool and just realized the walls might bow in once I start backfilling. What’s the best way to brace or support them until everything’s locked in with the deck?
I agree with what Kevin Marsh said about temporary bracing. From my experience, without support along the top, the walls can slowly move once the soil pushes back. I think you should take it slow and keep checking alignment, because you really only get one shot before everything is locked in.That’s a smart thing to think about before you start backfilling, a lot of people skip that step and regret it later. What we did on mine was use temporary cross braces made from 2x4s running across the pool, anchored to the top of each wall. That kept everything square and prevented the walls from pushing inward while we filled around the outside.
If your walls are made from concrete blocks, make sure the rebar and concrete fill inside the cores are fully cured first. Some folks also pour a small concrete collar or footing around the outside before backfilling, that helps lock the base in place. Go slow with the backfill, do it evenly on all sides, and keep checking the alignment as you go. Once the deck’s poured, the walls won’t move a bit, but until then, that bracing makes a big difference.
That’s a smart thing to think about before you start backfilling, a lot of people skip that step and regret it later. What we did on mine was use temporary cross braces made from 2x4s running across the pool, anchored to the top of each wall. That kept everything square and prevented the walls from pushing inward while we filled around the outside.
If your walls are made from concrete blocks, make sure the rebar and concrete fill inside the cores are fully cured first. Some folks also pour a small concrete collar or footing around the outside before backfilling, that helps lock the base in place. Go slow with the backfill, do it evenly on all sides, and keep checking the alignment as you go. Once the deck’s poured, the walls won’t move a bit, but until then, that bracing makes a big difference.
From what Kevin Marsh and William Walker explained about 2x4 cross-bracing, that’s a step many people skip. I helped on a smaller build where we added diagonal interior bracing and fully filled the block cores before backfilling. For me, the key wasn’t just the bracing but the pacing of the backfill. Go in stages, compact evenly, and check alignment on all sides so soil pressure doesn’t push unevenly. Until the deck or bond beam fully locks everything in, treat the walls as vulnerable and move carefully.I usually run 2x4 cross-braces across the pool and tie them to the top of the walls. Then you backfill slow and even while checking straight. Let the core fill cure first. Once the deck’s on, the walls stay put.